The Management Board of Budimex S.A. announces that on 08.05.2026 the Contracting Authority – Senatsverwaltung für Mobilität, Verkehr, Klimaschutz Umwelt selected the offer of BiGe (Bietergemeinschaft) composed of: Budimex S.A., Budimex Bau GmbH and Mostostal Kraków S.A. (Budimex Group companies) as the most advantageous in the tender procedure: “Construction of the Mühlendamm – Berlin Mitte Bridge. New construction TBW 1, TBW 2 and demolition TBW 2”.

Offer value: EUR 63,012,162 net

Date of commencement of works: 12 working days from the date of awarding the order.

Date of completion of works: 9 October 2028

Warranty period: 48 months

Warranty period: 48 months

Advance payment: none

Payment terms:

Transitional invoices: 21 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party,

Final invoice: 30 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party.

Bank guarantee of good performance: 5% of the gross price specified in the offer

Maximum value of the contractual penalty paid by the Contractor: 5% net salary

Other contractual conditions do not deviate from market standards.

The value of the offer exceeds the threshold of PLN 188,771 thousand net.