The Management Board of Budimex S.A. announces that on 09.06.2026r. The General Directorate for National Roads and Motorways, Rzeszów Branch, informed the Company that its bid was evaluated the highest in the tender procedure entitled."Design and construction of the bypass of Brzostek and Kołaczyce along the national road No. 73 with a length of approx. 13.4 km".

The above does not mean that the offer of Budimex S.A. was selected as the most advantageous, as the tender evaluation procedure has not been finally completed.

Offer value: PLN 356,877,592.30 net
Date of commencement of the contract: the date of conclusion of the Agreement by both Parties
Contract completion date: 39 months from the date of conclusion of the contract.
The time of execution of the Works does not include winter periods (i.e. from 1 December to 31 March). The time covered by the design includes winter periods (i.e. from 01 December to 31 March)
Warranty period: up to 15 years
Warranty period: 60 months from the date indicated in the Certificate of Takeover
Advance payment: from 1% to 10% of the Accepted Gross Contract Amount
Payment terms: 30 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party
Bank guarantee of good performance: 10% of the Accepted Gross Contract Amount
Maximum value of the contractual penalty paid by the Contractor: 20% of the Accepted Net Contract Amount

The Ordering Party reserves the right to claim supplementary damages transferring the amount of contractual penalties to the amount of the damage actually suffered, incurred or may arise in connection with the non-performance or improper performance of the Agreement by the Contractor.

Other contractual conditions do not deviate from market standards.

The value of the offer exceeds the threshold of PLN 188,771 thousand net.