The Management Board of Budimex S.A. informs that on 01.08.2025 the General Directorate for National Roads and Motorways, Katowice Branch, informed the Company that its bid was rated the highest in the tender procedure for the Construction of the bypass of Szczekociny and Goleniowy along national road No. 78.

The above does not mean that Budimex S.A.'s bid was selected as the most advantageous, as the bid evaluation procedure has not been finally completed.

Offer value: PLN 294,759,843.95 net
Date of commencement of works: date of conclusion of the Agreement by both Parties
Date of completion of works: 22 months from the Commencement Date (winter periods are not included in the time of completion of works)
Warranty period: up to 10 years
Warranty period: The warranty period for defects is 5 years from the date indicated in the Takeover Certificate
Advance payment: from 1% to 10% of the Accepted Gross Contract Amount
Payment terms: 30 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party
Performance bank guarantee: 10% of the Accepted Gross Contract Amount
Maximum value of contractual penalty paid by the Contractor: 20% of the Accepted Net Contract Amount
Maximum value of contractual penalty paid by the Employer: 15% of the Accepted Net Contract Amount

The Ordering Party reserves the right to demand supplementary compensation transferring the amount of contractual penalties to the amount of the actual damage suffered, arising or likely to arise in connection with non-performance or improper performance of the Contract by the Contractor.

Other contractual conditions do not deviate from market standards.
‎ ‎
The value of the offer exceeds the threshold of PLN 182,357 thousand net.