Construction of a section of the D35 motorway in the Czech Republic – selection of the Consortium's offer
The Management Board of Budimex S.A. announces that on 6 October 2026 it was informed that the Contracting Authority – the Czech Republic – the Ministry of Transport selected the offer of a consortium consisting of Budimex S.A. (10% share), Cintra Global B.V. – a company from the Ferrovial Group, to which the Issuer belongs (30% share), Strabag Motorway GmbH (40% share) and Invesis BV (20% share) (the "Consortium"), as the most advantageous in the competitive dialogue procedure for the PPP D35 project – Design, construction, financing, operation and maintenance of the sections of the D35 Opatovec – Staré Město and Staré Město – Mohelnice motorways, as well as the operation and maintenance of the adjacent sections of the D35 Litomyšl – Janov and Janov – Opatovec motorways (the "Project").
The contract will be implemented by the Consortium in the PPP formula and will cover the design, construction, financing, operation and maintenance (DBFOM) of new sections of the D35 motorway with a total length of 35.4 km and the operation and maintenance of two other sections of 17 km of the same motorway.
The concessionaire will be a special purpose vehicle under Czech law, which will be established by the members of the Consortium before the signing of the Concession Agreement. The shares in the special purpose vehicle will be acquired in accordance with the shares in the Consortium. The Concession Agreement requires the consent of the Government and then the Chamber of Deputies of the Parliament of the Czech Republic before it can be signed.
The Concessionaire will commission the construction part to a consortium in which Budimex Construction Prague s.r.o. with its registered office in Prague (a 100% subsidiary of the Issuer) will hold 40% and the remaining 60% will belong to Strabag SIS a.s. with its registered office in Prague. The estimated value of the construction part is in the range of 55% – 75% of the value of the offer. The General Contractor Agreement will be concluded no later than 7 days before the signing of the Concession Agreement and the Issuer will inform about it in detail in a separate report.
Offer value: CZK 71,323,843,913 (PLN 12,758,016,918.02). Some elements of the remuneration, including part of the payment for accessibility and construction costs, are subject to indexation by inflation rates with a base date of 31 December 2025.
Remuneration model: monthly availability fee during the concession period. Payments are made to the special purpose vehicle through the SFDI (State Transport Infrastructure Fund) within 30 days from the date of delivery of the invoice.
Adjustment of the accessibility fee: During the concession period, a mechanism is applied to adjust the monthly accessibility fee in the event of limited availability or failure to meet the motorway maintenance standards. The accessibility fee may also be adjusted for cases of improper performance of the contract during the construction work period.
Concession Term: 28 years from the Effective Date (defined below), which is the date of fulfilment of the conditions precedent set forth in the Concession Agreement.
Commencement date of the construction part: main works within 3 months from the Date of Entry into Force. Preparatory works may be carried out before the Date of Entry into Force, after the signing of the Concession Agreement.
Completion date of the construction part: the planned completion date is 70 months from the Date of Entry into Force. The Concessionaire is obliged to obtain the final occupancy permit within 108 months from the Date of Entry into Force.
Warranty period: During the concession period, the Concessionaire is responsible for the maintenance of motorway sections and improper performance of this obligation affects the amount of the accessibility fee it receives. After the expiry of the 28-year concession period, the Concessionaire provides a guarantee for a period of another 2 years for heavy maintenance works performed in the last 3 years of the concession period.
Collateral: (i) a bank guarantee for the closure of financing by the Consortium for a total amount of CZK 150 million (provided by the Consortium members in accordance with their participation in the Consortium), (ii) a bank guarantee securing the proper performance of the renovation works before the end of the concession period, the amount of which will be determined by an independent engineer on the basis of the results of the motorway condition review, and (iii) a guarantee for heavy maintenance works in the amount of 10% of the value of the works.
Conditions precedent provided for in the agreement: The entry into force of the material provisions of the Concession Agreement (the "Date of Entry into Force") is subject to the fulfilment of a number of conditions precedent, including in particular the closure of the financing by the Consortium, which should take place within 3 months of the conclusion of the Concession Agreement (with the possibility of extension to 4 or 6 months in certain cases). If the financing is not closed within the basic or extended deadline, the Concessionaire is obliged to pay a contractual penalty in the amount of CZK 150 million (approximately PLN 27 million), secured by the bank guarantee referred to above. Other conditions precedent include the conclusion of a number of agreements with the participation of the Ordering Party and the Concessionaire for the purpose of implementing the Project (e.g. an agreement with an Independent Engineer) and remain under the control of the parties to the Concession Agreement.
The contract is governed by Czech law with an arbitration clause under the rules of the International Chamber of Commerce in Paris. The seat of arbitration is Prague.
The other terms of the agreement do not deviate from the market standards for concession projects in the public-private partnership formula.
The net value of the offer exceeds PLN 188,771 thousand and the information has been classified by Budimex S.A. as confidential information.