Development of detailed designs and execution of civil works for phase I of the project entitled “Works on the E75 line along the Białystok – Suwałki – Trakiszki section, stage I – Białystok – Ełk section” - selection of the bid Budimex S.A.
The Management Board of Budimex S.A. announces that on 01.06.2021 PKP PLK S.A. selected the bid of Budimex S.A. as the most advantageous one in the tender procedure for Development of detailed designs and execution of civil works for phase I of the project entitled “Works on the E75 line along the Białystok – Suwałki – Trakiszki (state border) section, stage I – Białystok – Ełk section”.
The information that our bid had been evaluated the highest in the tender procedure was published on 31 March 2021 in current report No 25/2021.
Bid value: PLN 586,991,869.92 net.
Works commencement date: the commencement date shall be the day following the signature of the contract by the other party
Works completion date: 28 months from the Commencement Date
Guarantee period: 60 months
Statutory warranty period: 60 months
Advance payment: 10% of the Accepted Contract Amount for the basic scope less the gross value of the Conditional Amount
Payment terms: 30 days from the day of delivery of a correct VAT invoice to the Ordering Party by the Contractor
Bank performance bond: 5% of the total gross price.
Maximum amount of contractual penalty paid by the Contractor: 30% of works net value
The Ordering Party reserves the right to seek damages under general applicable rules if the amount of loss sustained exceeds the amount of the stipulated penalty.
Other terms and conditions of the contract do not differ from the market standards.
The bid value exceeds the threshold of PLN 167,645 thousand net.