The Management Board of Budimex S.A. announces that on 06.11.2025 the Development Directorate of the City of Gdańsk selected the offer of the consortium consisting of Budimex S.A. (Consortium Leader 84.09% share) and KZN Rail Sp. z o. o.(Consortium Partner share 15.91%), as the most advantageous in the tender procedure for the Construction of the Ujeścisko tram depot along with the construction of a retention reservoir in Gdańsk in the design and build formula.
The information that our offer was rated the highest in the tender procedure was published on 30.09.2025 in current report No. 56/2025.
‎ ‎
Value of the offer submitted by the consortium: PLN 260,777,899.00 net
‎ ‎
Date of commencement of works: from the date of signing the contract
‎ ‎
Completion date: 212 weeks from the signing of the contract
‎ ‎
Warranty period: 60 months

Warranty period: 60 months
‎ ‎
Down payment: none
‎ ‎
Payment terms: 30 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party
‎ ‎
Bank guarantee of good performance (or other collateral): 5% of the gross price

Maximum value of the contractual penalty paid by the Contractor: 20% of the gross price

 

Contractual penalties are not exclusive and the Ordering Party has the right to seek compensation on general terms, if the value of the damage exceeds the amount of these penalties.

Other contractual conditions do not deviate from market standards.
‎ ‎
The value of the consortium's offer exceeds the threshold of PLN 182,357 thousand net.