The Management Board of Budimex S.A. announces that on 9 November 2020, the Director of the Maritime Authority in Gdynia informed the Company that its bid had been evaluated the highest in the tender for Performance of civil works under project named: “Construction of a waterway connecting the Vistula Lagoon with the Gdańsk Bay — Part II”.

The aforementioned information does not mean selecting the bid of Budimex S.A. as the most advantageous one, as the procedure concerning the bid evaluation has not yet been finally completed.

Bid value: PLN 466,726,543.76 net

Works commencement date: on the contract date

Works completion date: 24 months from the conclusion of the contract

Guarantee period: 5 years

Warranty period: 5 years

Advance payment: up to 20% of the Approved Gross Contract Amount

Payment terms: 30 days from the day of delivery of a correctly issued VAT invoice to the Ordering Party by the Contractor

Bank performance bond: 5% of the Approved Gross Contract Amount

Maximum amount of contractual penalty paid by the Contractor: 15% of the Approved Gross Contract Amount

The Ordering Party reserves the right to seek damages under generally applicable rules if the amount of loss sustained exceeds the amount of the stipulated contractual penalty.

Other terms and conditions of the contract do not differ from the market standards.

The bid value exceeds the threshold of PLN 151,393 thousand net.