Design (in the scope of the railway industry) and comprehensive execution of construction works on the railway line No. 622 on the section F+J Podłęże R401 – Gdów / Podłęże R301 – Podłęże Balachówka as part of the project entitled: "Construction of a new railway line Podłęże - Szczyrzyc - Tymbark/Mszana Dolna and modernization of the existing railway line No. 104 Chabówka - Nowy Sącz - Stage II" - selection of the consortium's offer
The Management Board of Budimex S.A. announces that on 10.12.2025. The Contracting Authority – PKP Polskie Linie Kolejowe S.A. selected the offer of the Consortium consisting of: Budimex S.A. (leader of 75% share), Budimex Kolejnictwo S.A. (partner of 5% share), Ferrovial Construction (UK) Limited (partner of 20% share) as the most advantageous in the tender procedure for "Design (in the scope of the SRC industry) and comprehensive execution of construction works on the railway line No. 622 on the section F+J Podłęże R401 – Gdów / Podłęże R301 – Podłęże Balachówka as part of the project entitled: "Construction of a new railway line Podłęże – Szczyrzyc – Tymbark/Mszana Dolna and modernization of the existing railway line No. 104 Chabówka – Nowy Sącz – Stage II".
The information that our offer was evaluated the highest in the tender procedure was published on 14.10.2025 in current report No. 60/2025.
Offer value: PLN 2,592,999,232.00 net, including:
Basic scope: PLN 2,281,527,492.87 net (including substitute transport: PLN 10,000,000 net)
Conditional amount: PLN 306,521,739.13 net
Interface option: PLN 4,950,000.00 net
Date of commencement of works: The Commencement Date shall be the day following the signing of the Agreement by the other party
Date of completion of works: 38 months from the Date of conclusion of the contract
Warranty period: 72 months
Warranty period: 72 months
Payment terms: 30 days from the date of delivery of a correctly issued VAT invoice by the Contractor to the Ordering Party
Bank guarantee of good performance: 5% of the gross price for the Basic Range specified in the offer reduced by the Conditional Remuneration
Maximum value of the contractual penalty paid by the Contractor: 30% of the Contracted Contract Amount
The parties reserve the right to claim supplementary damages, transferring the amount of the reserved contractual penalties to the amount of the actual damage suffered.
Other contractual conditions do not deviate from market standards.
The value of the offer exceeds the threshold of 182,357 thousand net.