The Management Board of Budimex SA reports that on 24 October 2011 the consortium of companies Budimex SA (leader) and Ferrovial Agroman SA (partner) signed with Port Lotniczy Lublin SA a contract for the “Construction of a passenger terminal together with a technical building, a technical and garage building, an airport fire brigade building and the production of detailed designs in terms of electric power, electric, low-current, water-pipe, sewage, heating, cooling, mechanical ventilation and air conditioning systems and installations for the above construction structures under the task Development of the Regional Airport: Port Lotniczy Lublin S.A. (Świdnik).”

  • The contract is worth PLN 66,799,169.49 net
  • Commencement date: once the construction site has been handed over
  • Deadline: 9 months from the date of signing the contract
  • Guarantee period: 60 months
  • Financial terms and conditions:
    • Payment: 7 days from the date of delivering the invoice to the Contracting Authority
    • Bank guarantee of successful execution: 3% of the gross contractual amount
  • Penalties paid by the Contractor:
    • 0.01% of the net remuneration for each day of delay in completion of the works
    • 0.01% of the net remuneration for each day of the contractor failing to submit a correct and complete request for the issuing of a decision permitting the use of the construction structure
    • In the event of a delay in removing defects discovered in the guarantee period: 0.03% of the remuneration for each defective element of the works (penalty calculated on the value of a given item in the Lump-Sum Price Division table)
    • For withdrawing from the contract due to reasons attributable to the Contractor – 15% of the remuneration
  • In the event of the value of damage exceeding the stipulated penalties, the Contracting Authority is entitled to claim compensation on general terms

The contract value exceeds 10% of the equity of Budimex SA.