As part of the project, a new gas-oil boiler house was built with installations and auxiliary utilities, consisting of two water-tube boilers with a total nominal heat output of approx. 220 MW t. Each is equipped with a high-efficiency SCR exhaust gas treatment system. The investment meets the requirements of BAT (Best Available Techniques) conclusions and was implemented in the EPC (Engineering, Procurement and Construction) formula.

Realisation details

Full name

Kawęczyn Heating Plant

Category

Energy and industrial construction

Subcategory

ENERGY

Location

Warsaw

Start date

07.2017

End date

07.2023

Investor

PGNiG Termika (PGNiG Group)

Value

156,2 mln PLN