Home page > Budimex and Heilit + Woerner will complete the construction of the A4 motorway
Find in media:
Menu
About us
Offer
Electromobility
RES
Foreign markets
We are reaching out further and further. We are making strategic investments outside Poland.
Contractors
Investor relations
Investor information
Current quotes
See moreFinancial ratios
Current quotes
See moreESG
Safety
This is our priority and our common good. We are committed to ensuring that our employees and partners, once the work is completed, return home safely.
Media
About everything we do.
On a regular basis.
Find in media:
07.05.2013
The contract has a net value of PLN 798 million.
The scope of work includes the continuation of the following works:
• completion of the construction of a 34.7-kilometre section of the A4 motorway (Krzyż junction – Dębica junction)
Desert) along with access roads, as well as the reconstruction of local roads,
• construction of two junctions: Dębica – Żyraków and Dębica – Pustynia, 5 bridges, 9 viaducts in
motorway, 11 viaducts over the motorway and 3 animal crossings, culverts and
flyovers,
• construction of 64 access roads along the motorway, two motorway service areas –
Jastrząbka and Jawornik and the Straszęcin motorway maintenance circuit.
The consortium has 1.5 years from the date of signing the contract to carry out the work.