12.09.2013

Budimex has a building permit for the Białystok incineration plant!

Share article

The contract for the design and construction of the incineration plant, worth PLN 332.9 million net, was signed with Przedsiębiorstwo Usługowo-Handlowo-Produkcyjne “LECH” on 31 August 2012.

Budimex, as the leader (50.4 per cent of shares), will carry out this investment in a consortium with Keppel, Seghers, Belgium N.V and Cespa Compania Española de Servicios Publicos Auxiliares SA.

The incineration plant will be built at ul. Anders in Białystok. Thanks to the investment from over 90 to approx. 12 per cent. the amount of municipal waste that ends up at the municipal landfill in Hryniewicze will decrease. Annually, the new incineration plant will dispose of approx. 120 thousand tons of waste. In addition, electricity and heat will be generated from waste incineration.

The scope of construction works includes land development (administrative and office building, roads, parking lots, squares, networks, fences) and the construction of one complete municipal waste thermal treatment line, which consists of:

  • the segment of acceptance and temporary storage of delivered municipal waste,
  • segments of thermal waste treatment through incineration and energy recovery from incinerated waste,
  • the segment of recovered energy processing and discharge to the grid in the form of heat and electricity,
  • flue gas treatment segment,
  • slag processing segment with recovery of ferrous and non-ferrous metals,
  • segment for stabilization and solidification of ashes and solid residues from flue gas treatment.

The contractor’s obligations also include conducting final and operational tests and obtaining a permit to use the incineration plant.

The completion date of the works is scheduled for the end of December 2015.