20.11.2014

Expressway 5 from Kaczkowo to Korzeńsk put into service

Share article

In accordance with the contractual deadline, on 14 November 2014, Budimex completed works on approx. a 30-kilometre section of the S5 expressway on the Kaczkowo – Korzensko section.

The main route and access roads were put into service in mid-September, while in November the construction of Motorway Service Areas (MSAs) was completed.

Budimex’s task was to complete the construction of a 30-kilometre section of the S5 expressway after the previous contractor:

  • earthworks on the main route, transverse and service roads,
  • reinforcement of embankment slopes,
  • construction of foundations and surfaces,
  • execution of horizontal and vertical markings,
  • installation of traffic safety devices,
  • humus of slopes and planting greenery,
  • installation of noise barriers,
  • finishing works on engineering structures, in MOP buildings and industry works (lighting and telecommunications).

The contract with the Poznań branch of the General Directorate for National Roads and Motorways for the completion of the construction of the S5 expressway – Poznań (A-2 junction “Głuchowo”) – Wrocław (A-8 junction “Widawa”), section Kaczkowo – Korzensko (bypass of Bojanowo and Rawicz), was signed on 21 February 2014. Its net value is PLN 198.8 million.