06.10.2026
Budimex has completed a key stage construction new Oderberg Bridge in Germany. At the end of September Weighting about 330 tons The steel structure has been precisely displaced nad kanałem Havel-Oder waterway and mounted on prepared supports. The operation, carried out by Budimex SA and Budimex Bau GmbH over an active waterway, confirms the Company’s competence in the implementation of complex bridge projects on the German market.
New crossing It is about 50 meters long and 14.3 meters wide. To maintain navigability channel, the steel object was assembled in the square next to the target location, and then transported in its entirety. The process was divided on 19 precisely planned Do, in whose weight bridge gradually passed on between transport and support systems.
The structure was first lifted using hydraulic presses and placed on self-propelled transport platforms SPMT. Then it was moved towards the crossing axis and introduced on the A sliding track. In the decisive phase, part of the weight of the bridge was taken over by the specialized pontoon “Jurand”, allowing safe passage over the canal.
A pontoon about 35 meters long, 8.9 meters wide and maximum buoyancy about 518 tons equipped with support structure, ballast system and four stabilizing winches are used. In the most demanding moment took over about 182 tons loads. Precise control its location and controlled Forwarding weight allowed maintain the stability of the entire system.
– Sliding of a 330-ton structure on an active waterway required precise preparation, constant control of parameters and close cooperation between engineering teams and operators of specialized equipment. Safety remained our priority at every stage. Efficient implementation this operations confirms Competencies Budapest w Driving advanced projects bridges and strengthens our experience on the German market – says Eric Beecken, Manager Contract at Budimex Bau GmbH.
Safety was one of the key elements of the project. The team at Ongoing controlled forces acting on fulcrums, position construction, weather conditions and the water level in the canal. Applied solutions allow to safely stop the operation at any time, and in in the event of an unforeseen event – withdraw the bridge towards land.
Project in Oderberg assumes Replacing a steel bridge z 1958 new facility that will preserve the historical form, colors and nature of the original crossing. The order worth nearly EUR 12 million gross is being carried out by Budimex SA and Budimex Bau GmbH on behalf of the National Authority ds. Brandenburg Roads. Scope works It includes the demolition of the old bridge, partial reconstruction of the abutments, construction and installation of a new steel structure, as well as road and infrastructure works. The investment is another example of using Budimex’s experience in demanding infrastructure projects outside Poland.