24.08.2020

Progress of work on the construction site of the S61 section. High – Raczki at the halfway point

Share article

The progress of works on the S61 Wysokie – Raczki expressway section is currently about 50%. Budimex is the general contractor for this task.

The works are ahead of schedule by several months. The earthworks are already 90% complete. Work on the pavement structure is already underway. A 2 km long concrete test section is already being tested. Bituminous works on transverse roads are also underway. The construction of engineering structures – viaducts and passages is 40% advanced. Every day, about 170 units of equipment work on the construction site, approx. 470 people.

The planned date of completion of works on the entire twenty-kilometer section is June 2021. The works carried out in the design and build formula began in July 2018. The original value of the task is PLN 393 million net.

Pobierz plik - obrazek

Michal Wrzosek Budimex Sa S61 Wysokie Raczki