Contact us!
Contact information for the person responsible for the communication
Menu
About us
Offer
Electromobility
RES
Foreign markets
We are reaching out further and further. We are making strategic investments outside Poland.
Contractors
Investor relations
Investor information
Current quotes
See moreFinancial ratios
Current quotes
See moreESG
Safety
This is our priority and our common good. We are committed to ensuring that our employees and partners, once the work is completed, return home safely.
Media
About everything we do.
On a regular basis.
Find in media:
27.10.2021
The progress of works on the S5 Nowe Marzy – Dworzysko section implemented by Budimex has already exceeded 50%. Construction works are focused on the main route of the road to ensure the maximum capacity of the new route as soon as possible. We plan to complete the works on the main road by the summer of 2022. The entire investment will be completed by the end of 2022 – in accordance with the contractual deadline.
Budimex signed the contract for the construction of this section with the investor: the General Directorate for National Roads and Motorways in Bydgoszcz in April 2020. The works are carried out on a section of the S-5 expressway from the Nowe Marzy junction (without the junction) to the Dworzysko junction (with the junction) with a length of 23.3 km.
Budimex continues the work after another general contractor, which completed only part of the works (29%). The contractual deadline for the construction is 22 months, excluding winter months.
Scope of work on the S5 – Nowe Marzy – Dworzysko:
Bridge scope – basic information:
S5 Nowe Marzy Dworzysko