As part of the investment, a taxiway was built for the DK-N2 rapid exit with the DS-1 runway and the Holding Point in front of the threshold 29 of the DS-1 runway. The DK-E2 taxiway was also renovated. The scope of work included tasks in the field of airport and road and construction and construction segments, as well as drainage, electrical and teletechnical infrastructure.

Realisation details

Full name

Airport infrastructure F. Chopin

Category

Infrastructure construction

Subcategory

AIRPORTS

Location

Warsaw

Start date

03.2019

End date

12.2019

Investor

State Enterprise "Polish Airports"

Value

136 mln PLN