Railway line no. 133 – Trzebinia – Krzeszowice
![](https://budimex.pl/app/uploads/2024/04/103_Trzebinia-2-scaled.jpg)
As part of the investment, 12 tracks with a total length of almost 9 km were modernized, including: 13,000 pcs. sleepers, 50,000 tons of ballast, 26 turnouts, 10,500 m of overhead contact line, as well as 3 platforms, including one single-edge and two island platforms. In addition, the project included the construction of an underground passage, a footbridge with lifts and a ten-span road flyover with a reinforced concrete beam structure.
Realisation details
Full name
Railway line no. 133 - Trzebinia - Krzeszowice
Category
Railroad construction
Location
Trzebinia - Krzeszowice
Start date
10.2017
End date
06.2023
Investor
PKP Polskie Linie Kolejowe SA.
Value
320 mln