The entire section F of the A1 motorway is 20 km long, including the 12.5 km section implemented by Budimex, which was 50% completed at the time of taking over the construction site. As part of the project, 132,000 m2 of cement concrete substructure and 180,000 m2 of cement concrete pavement and 85,000 m2 of cement concrete pavement were completed. tons of mineral and bituminous mixtures. We completed the interrupted construction of 13 bridges and 10 culverts, we constructed noise barriers, rainwater drainage, reconstruction of the W400 water main and construction of power lines and lighting. We have also completed the construction of five transverse roads. The contract was completed ahead of schedule.

Net value: PLN 155.1 million

Realisation details

Full name

A1 motorway Częstochowa bypass

Category

INFRASTRUCTURE

Subcategory

Roads

Location

Czestochowa

Start date

07.2019

End date

12.2019

Investor

GDDKiA

Value

154 mln PLN