Budimex SA has commissioned over 25 km of the S17 dual carriageway expressway, together with the accompanying infrastructure and engineering structures. The works resulted in the creation of m.in on this route. three road junctions – Górzno, Gończyce and Trojanów, and two Motorway Service Areas. This route consists of two sections, on which a total of approx. 328 thousand tons of cement concrete, approx. 155 thousand tons of bituminous masses and approx. 3 million tons of embankments. The road is made in concrete surface technology. The scale of the investment is evidenced by the numbers associated with it. Only in the case of the first task, the work was carried out with the use of 90 hardware units.

The over 12-kilometre section of the road from Garwolin to Gończyce has 45 ecological and hydrological-ecological culverts, two bridges, 6 road viaducts and two road junctions. The first of them, called Górzno, will replace the existing intersection with the county road, while the Gończyce junction is intended to connect the provincial road with the S17 expressway. A kilometre of road in this section runs in a 9.5 m deep trench. At the section between Garwolin and Gończyce, the Road Maintenance Circuit, which includes m.in, was also erected. a workshop and garage building or a warehouse, housing approx. 30 tons of road salt.
The road investment located in the Garwolin district, in the municipalities of Sobolew and Trojanów, is over 13 km long, and on its route there is the Trojanów junction and two Motorway Service Areas, named MSA Wola Korycka and MSA Mroków. As in the case of the first section, also in this project, a section of the road runs in a trench. Its depth is 13 m.

Realisation details

Full name

S17 Warsaw – Lublin

Category

INFRASTRUCTURE

Subcategory

Roads

Location

Garwolin-Kurów route

Start date

03.2017

End date

07.2019

Investor

General Directorate for Roads and Motorways in Lublin

Value

490 mln PLN