Implementation of the task entitled: Section A - Construction works on railway lines No. 201 section Kościerzyna – Somonino and No. 214 Somonino – Kartuzy implemented as part of the project "Works on the alternative transport route Bydgoszcz – Tricity" – Budimex SA's offer rated the highest
The Management Board of Budimex S.A. announces that on 28.06.2024. PKP Polskie Linie Kolejowe S.A. informed the Company that its bid had been rated the highest in the tender procedure for the Implementation of the task entitled: Section A – Construction works on railway lines No. 201 section Kościerzyna – Somonino and No. 214 Somonino – Kartuzy implemented as part of the project “Works on the alternative transport route Bydgoszcz – Tricity”.
The above does not mean selecting the bid of Budimex S.A. as the most advantageous one, as the procedure concerning the bid evaluation has not yet been finally completed.
Offer value: PLN 1,284,235,699.12 net
Basic order part A:
Net price: 1 158 734 402,53 PLN
Gross price: 1 425 243 315,11 PLN
Basic order part B:
Net price: 117 121 919,95 PLN
Gross price: 144 059 961,54 PLN
Option No. 1:
Net price: 5 555 037,24 PLN
Gross price: 6 832 695,81 PLN
Option No. 2:
Net price: 2 824 339,40 PLN
Gross price: 3 473 937,46 PLN
Works commencement date: the day following the date of signing the contract
Works completion date:
1) Implementation period for the Basic Order (Time for Completion): 42 months from the Commencement Date
2) Implementation period for Option 1: 108 months from the date of expiry of the Defect Reporting Period for the Basic Scope
3) Implementation period for Option 2: specified by the Ordering Party in the statement on using Option 2, but no later than by the date of expiry of the Defect Reporting Period for the Basic Order, and if the Ordering Party uses Option 1 – until its completion.
Warranty period: 72 months
Warranty period: 72 months
Advance payment: no more than 10% of the Accepted Contract Amount for the Basic Scope
Payment terms: 30 days from the date of delivery of a correctly issued VAT invoice to the Ordering Party by
Contractor
Bank performance bond: 5% of the total gross price for the Basic Scope specified in the bid less the gross costs of replacement transport services, subject to the provisions of item 21 of the Instructions for Contractors (IDW).
The maximum value of the contractual penalty paid by the Contractor:
The total amount of penalties charged in this Sub-Clause shall not exceed 20% of the net value of the Works in respect of Part A of the Basic Scope, with a stipulation that if the contractual penalty referred to in item t) (penalty for withdrawal from the Contract for reasons attributable to the Contractor) has been charged, the total amount of penalties charged shall not exceed 30% of the net value of the Works in respect of Part A of the Basic Scope.
Other contractual conditions do not deviate from market standards.
The value of the offering exceeds the threshold of 196,030 thousand. PLN net.