The contract included the construction of a new runway (NDS) with a width of 45 m and a length of 3,200 m made of cement concrete with a total area of 2 thousand tonnes. m2 with bands made of mineral and asphalt mixtures 2×7.5 m wide, construction of blow-off planes and construction of taxiways and technical, fire, patrol and access roads made of mineral and asphalt mixtures with a total amount of 53 thousand. ton, construction of a rainwater drainage system, reconstruction of the radio navigation system and construction of power and teletechnical networks for radio navigation and meteorological devices along with navigation lighting.

Realisation details

Full name

Construction of a new runway at Katowice Airport

Category

Infrastructure construction

Subcategory

AIRPORTS

Location

Pyrzowice

Start date

02.2012

End date

11.2014

Investor

Upper Silesian Aviation Group

Value

142 mln PLN